16 January 2005

Two areas of attack today, firstly one of the roads into the carriage shed needed lifting by about half a mile to level the two up in preparation for other works going on in the future, and secondly there was a large amount of excess ballast on the track around Leamland bridge.

new sleepers
Firstly, some of the sleepers had to be changed, as they were a little worse for wear...

lift
After that, the approach to the shed was lifted in a couple of stages, as there is a limit to the amount you can lift in one go

shovels
The gang forms an orderly queue waiting for the next bus to turn up....